SPACE ONLY STAND PLANS
As a Space Only Exhibitor, you need to appoint a competent contractor to design and build your stand. Proposed stand designs must be reviewed prior to build to assess the structural integrity.
As an Exhibitor, you also have a responsibility to ensure the health,
safety and welfare of all members who may participate in the build of your
stand, including contracted companies during build, show and dismantling.
When appointing your Stand Contractor, consider the following:
- Request references, check their experience and previous work within the country where the event takes place
- Check
the number of stands the Contractor has committed to for this event
- Confirm
whether they will be sub-contracting
- Confirm
the number and competence of workforce allocated to your stand
- Check
their health & safety policies
- Check
if they have adequate public liability insurance
- Confirm
the time required to build the stand – see Event Times section of this OEM
for further information
- Agree
a completion time on final build day – providing you time to prepare for
show open within the build-up time schedule
- Insist
on a financial guarantee against the agreed completion date and time and
do not pre-pay the entire sum before the work has been completed to your
satisfaction
Please note that your nominated contractor has a duty of care to
ensure the health, safety and welfare of their employees, sub-contractors and
the associated activities being undertaken without impact to others
safety.
SPACE ONLY STAND PLAN SUBMISSION
All exhibitors building space only stands must submit stand plans for inspection and approval to Abraxys Global by 27 September 2026
Exhibitors are permitted to construct stands up to the height of six (6) metres. Refer to the BUILD HEIGHTS section of our Rules & Regulations [insert link] for further information
- Detailed technical plans & 3D rendering at a scale of 1:50 detailing:
please provide a set of full technical drawings that is signed and stamped by a certified structural engineer. This is required as there are structural elements or additional loads that could affect structural integrity.
- side & height elevations
- electronic plans to scale in English
- structural calculations for the stand
- structural calculations for stairs and steps (where applicable)
- Step and stair details showing tread, riser and handrail dimensions along with a clear constructional diagrams
- evacuation plan showing all necessary smoke detectors, escape route signage and locations of fire extinguishers
- stand number & exhibitor name
- Details of any rigging requirements or hung elements
- Details of any high - risk exhibits
- Any rigging must be plotted on a dwg plan of the exhibition hall and submitted with your stand plans - please contact Abraxys for a copy of this dwg if you need it
- On-site contact person and mobile phone number
- Detailed information about the materials being used, including up-to-date fire resistance certificates.
- Risk Assessment
- Method Statement
- Inspection Certificate from an independent Certified Structural Engineer
Any costs relative to obtaining proper certification are at the cost of the exhibitor.
It is recommended to submit plans, whenever possible, well in advance of the applicable deadline so that if any change is required it will not affect the installation schedule. Once approved by DECC/Abraxys Global/GSMA has been given, no changes can be made to the Stand Plans.
Exhibitors and contractors must adhere to the following guidelines when submitting their plans:
- Stands built on-site must adhere to the submitted and approved stand plans. Onsite, Abraxys will conduct inspections during the assembly period and will have the right to stop construction and take any necessary action against the exhibitor and contractor in the event that regulations or stand plans are not complied with. Exhibitors will be entirely liable for any onsite changes which have to be made to the stand or stand plan arising from non-compliance and will be responsible for covering all costs associated with this or any action taken by DECC or Abraxys to rectify the problem.
- All stand design and constructions must comply with the guidelines, rules and regulations laid down in the manual as well as those issued by the relevant government authorities.
- Detailed drawings must be submitted, including elevations, layout plans and 3D perspective view with dimensions and heights illustrating the design and list of materials, incomplete plans will not be accepted and may affect exhibitors and contractors’ rights to build on-site.
- Stand plans must also clearly indicate the name and signature of the contractor, along with address, telephone number and email address. The stand name and stand number should also be indicated. Official pre-approval notices will be sent back to the person submitting the plans.
- Stand plans must be submitted in a recognised metric scale of no less than 1:50. Plans must be sent to Abraxys by email in JPEG or PDF format or submitted online.
- Only upon approval by DECC and Abraxys can the exhibitor and its registered contractor commence work on-site.
For further information regarding this regulation please contact:
Abraxys Global
Tel: +44 (0)20 8747 2045 (UK)
Email:mwcdoha@abraxys.com
RISK ASSESSMENT - guidance notes
Do this for the build-up, exhibition open days and dismantling. Weigh up whether you have taken enough precautions or should do more to prevent harm. The important aspect is whether a hazard is significant, and whether you have covered it by satisfactory precautions and controls, so that the risk is small.
If you are building a booth, your risk assessment must also include a detailed analysis of all the risks associated with your booth build, fitting and removal (e.g., working at height, use of tools, risk of fire, hazardous substances, heavy loads, live electricity, etc); and again what precautions and control measures you will implement in order to lower the risk to a safe level.
If you are building a large or complicated booth, or are involved in unusual activities during the exhibition, you may need to seek the assistance of a qualified Health & Safety professional.
The following is your step-by-step guide to completing a risk assessment:
Ask yourself:
| Potential hazards:
|
- Who will be affected by your work and at most risk?
- Who are your employees, contractors or exhibitors on or near your booth?
- How will your visitors be affected?
- Groups include staff, contractors, guests, venue service staff, among others
Write down the significant hazards and conclusions. You must also tell your employees about your findings. You should be able to demonstrate that you have made a suitable assessment by identifying what the main hazards are, who might be affected, that the precautions are reasonable, and the risk is low.
Step 5: Review your assessment
Review your assessment and revise as necessary, inevitably new plans may develop and new observations may be made which could lead to new hazards requiring an assessment. It is good practice to review your assessment from time to time to make sure precautions are working effectively, allowing you to learn by experience.
METHOD STATEMENT
A method statement describes in a logical sequence how a job is to be carried out in a safe manner and without risks to health. It includes risks identified in the risk assessment and will elaborate with a detailed, step-by-step written description of how the work will be undertaken in a safe and controlled manner.
In all stand-building cases (especially steelwork erection and lifting), the foreman and / or the principal contractor should draw up a specific method statement and go through it with your contractors in advance of the event.